11) If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
Answer is:
3.5 and 25/36
Related Structural Engineering II MCQ with Answers
Answer is:
identify the activities, which can be delayed without affecting the total float of succeeding activity
Answer is:
free float and independent float both must be zero