8) In the network shown in Fig. the earliest start time of activity 5-6 is (the number on the arrow shows duration of the activity)
Answer is:
9
Related Structural Engineering II MCQ with Answers
Answer is:
both activities 2—3 and 4—6 are completed
Answer is: